Story Contracting has successfully completed the replacement of the River Sheaf railway bridge in Sheffield on behalf of Network Rail, marking a major milestone in the delivery of the project.
The works involved the removal of the existing bridge structure, which dated back to before 1905, and the installation of a new 70-tonne bridge deck designed to support the long-term reliability and resilience of the railway.
Delivered during a carefully planned 52-hour railway possession, the project required the coordination of multiple specialist teams and complex lifting operations. More than 3,000 people-hours were invested throughout the works, culminating in the successful installation of the new structure and the reopening of the railway as planned.
Alongside the bridge replacement, the programme included track removal and reinstatement, waterproofing works and drainage improvements to help protect the asset for future generations.
The successful delivery of the scheme was made possible through close collaboration between Story Contracting, Network Rail and project partners, with teams working around the clock to complete the critical programme of works safely and efficiently.
Tom Grainer, Lead Portfolio Manager at Network Rail said: “Well done and thanks to everyone who has been involved in the bridge replacement and behind the scenes since the project started. It’s great to see it complete.”
Story Contracting and Network Rail would like to thank local residents, businesses and rail passengers for their patience and understanding throughout the works. Their support helped enable the safe and successful delivery of this important infrastructure upgrade.