Bombo Burn Scour Protection Works
The bridge at Bombo Burn required extensive remediation in the form of scour protection works, as well as vegetation management and masonry repair works.
Network Rail
Circa £500k
Bombo Burn
The scope of the works involved:
- Site Mobilisation & Establishment Works
- Installation of & Removal of Temporary Damming System
- Excavation & Profiling of Riverbed
- Installation of Reinforced Concrete Invert
- Installation of Rip Rap
- De-vegetation of Structure & Masonry repairs
- Demobilisation & Reinstatement Works
The project was able to celebrate success
 and demonstrated best practice within the
 following areas:
- Completion of works within programme, budget
 and with no accidents or incidents within a
 logistically challenging location.
- The use of an effective over pumping damming
 solution to maximise productivity whilst
 maintaining a robust method of safe working
 around the structure with no disruption to rail
 traffic.
- The revision of design levels to mitigate any risk
 which may be present of implementing works given
 the shallow foundations present supporting the
 structure.
- The creation of a complete dry working area for an
 effective and prolonged period to allow concrete
 works to take place.
- The success of delivering the project whilst adapting
 to working within the Covid 19 pandemic.
- The safe and efficient delivery of the whole works
 package during challenging weather and water level
 conditions.
Our project team worked in close collaboration with NWR,
 environmental agencies and designers to ensure various
 specialist works could be completed within the allocated time
 frame for working within the watercourse, with solutions
 such as an effective temporary damming system & ensuring
 the works did not jeopardise the shallow foundations present
 supporting the structure.
Our project team also effectively planned works and used an
 innovative technology to enable the works to be planned and
 implemented successfully in ever changing weather and water
 level conditions
Circa 200t
Rip Rap installed
Circa 90 m3
concrete poured